Final straight

Building of the first semi-submersible floating drilling rig being under construction at Vyborg Shipyard by the order of Gazflot LLC has reached the completion stage. On the 2nd of September there was performed loading of the fourth level of the corner columns which installation will be finished in the end of September of this year.

Also there is performed the final installation of electrical equipment, and it is planned to start works on the cable drawing in the pontoons already by the end of September. Simultaniously there are carried out works on room painting and shell plating of the platform.