Works on section assembly for the second SSFDR are being performed
In process of construction of NB 107 there are being executed welding and section assembly works of the first, second and third levels of columns for their further assembly in volume. There continued works on formation of fore, middle and aft columns of the first level, erection of the columns is planned to be executed early in September. In the internal rooms of the pontoons there are installed vertical ladders to the main deck, installation of the systems and bottom and outboard fittings is well under way. Painting works of closed rooms of the left and right pontoons are being performed.